Two companies filed complaints this month asking the Federal Energy Regulatory Commission, or FERC, to rewrite capacity market rules. FERC is the federal agency that approves the rules wholesale power markets run on. Exelon filed on November 3 against PJM, the grid operator that serves 13 states and Washington, D.C. Invenergy Transmission filed on November 4 against MISO, the operator of a separate grid market in the middle of the country. FERC A capacity market is where a grid operator pays power plants and other suppliers ahead of time to promise power will be there when demand peaks. Exelon
What did Exelon ask FERC to change?
PJM holds its main capacity auction in May, three years before the year the power is delivered. PJM Manual 18 Exelon asks FERC to replace it with a prompt auction held about two months before each delivery year starts, beginning with the year that starts in 2030. Utility Dive The December 2026 auction would go ahead as planned. Under the current schedule, the auction for 2030/31 is set for May 2027, and Exelon asks to push it to about March 2030. Exelon argues that buying capacity three years ahead is no longer just and reasonable, which is the test FERC uses when someone asks it to change a market rule. Energy Choice Matters Exelon asked FERC to rule by January 31, the last day before PJM publishes the planning figures for that May auction. Utility Dive
Why the timing matters for a large AI data center
Each utility or supplier serving customers in PJM pays a daily capacity charge. The charge equals its share of the region’s capacity need multiplied by the price the auction set for its zone. PJM Manual 18 That charge reaches commercial electric bills, so the auction affects how fast AI data center growth shows up in operating budgets. ChargedUp
PJM’s July auction for 2028/29 cleared at its price cap and still fell about 6,800 megawatts short of its reliability target. A megawatt is a unit of electric power. PJM says most of its forecast growth comes from new large loads, mainly AI data centers. MLQ
The utility company says a forecast can count dozens of new AI data centers that are delayed or cancelled. Customers would still pay for capacity bought years earlier on that forecast. Exelon The price cap FERC extended in April covers delivery years only through May 2030. Exelon release Exelon says moving the 2030/31 auction would keep customers from an uncapped price jump it expects next spring. Energy Choice Matters Exelon also says a prompt auction does not guarantee lower prices and does not add the new power plants PJM needs. Exelon
What Invenergy wants from MISO
Invenergy builds merchant power lines. A merchant line is a privately funded long distance line. It earns money from customers who sign contracts with it, not from regulated rates that FERC sets. Utility Dive
Invenergy’s complaint says MISO counts the capacity these lines bring in when it decides how much capacity to buy. Counting the lines lowers the amount MISO buys. MISO’s rules do not let the line’s owner sell that capacity or be paid for it, so other customers get the benefit for free, Invenergy argues. RTO Insider Invenergy says its planned Grain Belt Express, a 5,000 megawatt line of about 800 miles from Kansas to Indiana, could supply more than 1,800 megawatts of capacity under one counting method. Without a capacity payment, Invenergy says, a merchant line has nothing to sell inside MISO. Megaproject
| Rule | Today | What the complaint asks |
|---|---|---|
| When PJM buys capacity | Three years before delivery | About two months before delivery |
| PJM auction for 2030/31 | Set for May 2027 | Moved to about March 2030 |
| PJM auction in December 2026 | Goes ahead as planned | Still goes ahead as planned |
| Merchant lines in MISO buying decisions | Counted to lower the amount bought | Still counted |
| Payment to merchant line owners in MISO | No way to be paid for capacity | Paid as capacity suppliers |
The timeline
PJM says it is reviewing Exelon’s complaint and will respond at the appropriate time. PJM is also running its own review of its capacity market. More than 30 stakeholder papers are scheduled for discussion at a workshop on November 13. Utility Dive via Yahoo FERC lists both complaints as pending, under case numbers EL27-11 for Exelon and EL27-12 for Invenergy. FERC has not ruled on either one.
Tomorrow’s topic
The Texas bills to repeal the data center sales tax exemption.