What did ISO New England file?
ISO New England runs the power grid for the six New England states. On November 13, 2026, it filed proposed rule changes with FERC that would govern how very large electricity users connect to that grid. FERC is the Federal Energy Regulatory Commission, the federal agency that approves the rules grid operators must follow. The New England Power Pool and the committee for the region’s transmission owners joined the filing. ISO New England
The filing answers a FERC order issued June 18, 2026. That order said the region’s tariff appears unjust and unreasonable because it has no clear rules for large loads. A tariff is the rulebook, filed with FERC, that sets the terms of grid service. FERC order
The proposal defines a large load as a commercial or industrial site whose peak demand reaches 50 megawatts or more. A megawatt is a unit of power. The definition is not limited to AI data centers, so it reaches factories as well. ISO New England summary
Three ways a large load could connect
The first option is firm service. A site on firm service gets the same priority as every other firm customer on the grid. In return, the required grid upgrades must be finished. The site must also bring new capacity, meaning new power supply committed to match its demand. ISO New England says the detailed rules for that supply requirement will be worked out with stakeholders in 2027. ISO New England
The second option is interim service. It is a temporary, lower priority service for a site still working toward firm status. It lasts up to seven years or until the needed upgrades are in service, whichever is longer.
The third option is permanent non firm service. It requires no new supply and may need fewer upgrades. The tradeoff is a price trigger that also applies to interim service. When the power price at the site reaches $250 per megawatt hour, the site must cut its use or run its own eligible generation. A megawatt hour is one megawatt used for one hour. ISO New England says prices in the region reach $250 in about 1% of hours today. ISO New England
| Issue | Under the current tariff | Under the proposal |
|---|---|---|
| Who counts as a large load | No separate category exists | Commercial or industrial site at 50 megawatts or more |
| Study for a new large load | No study path written for large loads | Study completed in 90 days in most cases |
| Top priority service | Ordinary network service | Firm only after upgrades and new supply |
| Cutting use when power is scarce | No price trigger | Non firm sites cut use above $250 |
| Generation on the same site | Can offset load for some charges | Large loads may not offset at all |
Application fees, deposits and schedule under the ISO New England proposal
An application would carry a $50,000 fee that is never refunded and a $150,000 study deposit. The site would also post a readiness deposit of $10,000 per megawatt. A 50 megawatt site would therefore post $500,000 for that deposit alone. ISO New England would post the queue publicly, including each site’s peak demand, location and requested service. ISO New England summary
The schedule is long. The application and study process would start June 1, 2027. The new transmission services would start June 1, 2028. ISO New England presentation
One part of the package drew opposition. The transmission owners proposed their own cost recovery agreement. FERC described this kind of agreement as a contract requiring the large load’s customer to pay toward upgrades even if the site uses less power or is never built. The New England Power Pool’s top committee voted for most of ISO New England’s proposal. It did not support the transmission owners’ approach to cost recovery. RTO Insider
What FERC still has to decide
None of these rules binds a developer until FERC accepts them. FERC put the June case on hold in August. It set November 16, 2026 for responses and December 16, 2026 for answers to those responses. It also said a filer that proposed its own rule changes by November 16 would not have to respond separately, and the case would stay on hold. FERC order
Outside parties may comment on the filing within 30 days after it was made. Construction Review FERC may accept the proposal, reject it, or require changes. The cost recovery approach is the one part of the filing the power pool’s top committee did not support. FERC’s June order also told the region that any new rules should leave time to finish deals already close to signing. FERC order