What did the commission order?
On November 16, 2026, the North Carolina Utilities Commission approved new rates for Duke Energy Carolinas and created a separate rate schedule for large data centers. The commission is the state body that decides what investor owned utilities may charge. Its order finds that Duke’s existing and proposed rate schedules do not properly assign the costs and risks of the new equipment these customers need. The order warns that if expected demand never arrives, or a customer leaves early, the cost of plants and lines lasting 30 years or more could shift to other North Carolina customers. North Carolina Utilities Commission order
New rates take effect January 1, 2027. Duke Energy Demand is measured in megawatts, a unit for how much power a site draws at one time. Duke’s two Carolinas utilities signed contracts for 6,700 megawatts of new large customer demand between March 2024 and April 2026, and data centers account for 92 percent of it. WRAL
Which customers the new schedule covers
The schedule applies to a customer with demand of at least 50 megawatts that functions, or is expected to function, as a data center. Under the order, a facility counts as a data center if its main demand comes from storing, processing or moving data, or if that computing demand alone reaches 50 megawatts. The order also says the date a customer signed its service contract will not decide whether the new terms apply. An existing customer that adds new demand after the order date is held to the same protections for that added demand. North Carolina Utilities Commission order
That differs from the agreement Duke filed on October 6 with the state’s consumer advocate office and several large technology companies. The agreement would have covered any customer of 50 megawatts with steady high use, or 150 megawatts at any use, and only contracts signed on or after June 1, 2026. Settlement filing The commission approved every other agreement in the case without change, but not that one. Duke Energy Carolinas fact sheet Two commissioners agreed with the result but wrote that the rules should cover all large users, not only data centers. Energy News Beat
What a new large customer must pay and promise
A data center above 100 megawatts must sign a contract of at least 15 years. It must pay for at least 75 percent of the demand it reserves, even in months it uses less. It pays upfront for equipment built only for it, such as a substation. For network upgrades, which are improvements to the shared lines that carry power across the grid, it posts a letter of credit. A letter of credit is a bank’s promise to pay Duke if the customer does not. A customer that ends its contract early owes set damages. Duke Energy Carolinas fact sheet
The order also requires Duke to file an estimate of each customer’s share of network upgrade costs for the commission to review and approve. Its newest term is a stranded generation charge. That charge covers the part of a new power plant left unpaid if a data center stops service before the plant wears out. The order estimates it from a model gas plant with a 35 year life, at $67,357 per megawatt each year. A stakeholder group will develop a permanent method for this charge, a standard service contract, and the method for assigning upgrade costs. North Carolina Utilities Commission order Duke told investors it is still assessing this part of the order. Duke Energy Form 8-K
| Term | October agreement | Commission order |
|---|---|---|
| Who is covered | Any customer of 50 megawatts with steady use, or 150 megawatts | Data centers of at least 50 megawatts |
| Contract signing date | Only contracts signed on or after June 1, 2026 | Signing date does not decide coverage |
| Shared grid upgrades | Bank guarantee, direct charge only after a future method | Duke files each customer’s estimated share for commission review |
| New power plants | No separate charge | Stranded generation charge of $67,357 per megawatt each year |
| Rate schedule | Duke’s existing schedule for large steady users | A new schedule only for data centers |
A commissioner dissents in part over costs left to other customers
In the companion order for Duke Energy Progress, one commissioner dissented in part. He wrote that the plants are built to last about 35 years while the contracts run 15. He argued that even when a departing data center pays everything required, about half of the remaining plant cost can stay with other customers. Carolina Journal
He gave an example of a 500 megawatt data center that could require about $674 million of new equipment. If that customer left after 15 years, he wrote, it would pay about $338 million, and the other $335 million would fall on remaining customers. Environmental Defense Fund He would have required data centers to pay in advance for the generation and transmission their demand needs.