North Carolina sets new rules for large data centers on Duke's grid

What did the commission order?

On November 16, 2026, the North Carolina Utilities Commission approved new rates for Duke Energy Carolinas and created a separate rate schedule for large data centers. The commission is the state body that decides what investor owned utilities may charge. Its order finds that Duke’s existing and proposed rate schedules do not properly assign the costs and risks of the new equipment these customers need. The order warns that if expected demand never arrives, or a customer leaves early, the cost of plants and lines lasting 30 years or more could shift to other North Carolina customers. North Carolina Utilities Commission order

New rates take effect January 1, 2027. Duke Energy Demand is measured in megawatts, a unit for how much power a site draws at one time. Duke’s two Carolinas utilities signed contracts for 6,700 megawatts of new large customer demand between March 2024 and April 2026, and data centers account for 92 percent of it. WRAL

Which customers the new schedule covers

The schedule applies to a customer with demand of at least 50 megawatts that functions, or is expected to function, as a data center. Under the order, a facility counts as a data center if its main demand comes from storing, processing or moving data, or if that computing demand alone reaches 50 megawatts. The order also says the date a customer signed its service contract will not decide whether the new terms apply. An existing customer that adds new demand after the order date is held to the same protections for that added demand. North Carolina Utilities Commission order

That differs from the agreement Duke filed on October 6 with the state’s consumer advocate office and several large technology companies. The agreement would have covered any customer of 50 megawatts with steady high use, or 150 megawatts at any use, and only contracts signed on or after June 1, 2026. Settlement filing The commission approved every other agreement in the case without change, but not that one. Duke Energy Carolinas fact sheet Two commissioners agreed with the result but wrote that the rules should cover all large users, not only data centers. Energy News Beat

What a new large customer must pay and promise

A data center above 100 megawatts must sign a contract of at least 15 years. It must pay for at least 75 percent of the demand it reserves, even in months it uses less. It pays upfront for equipment built only for it, such as a substation. For network upgrades, which are improvements to the shared lines that carry power across the grid, it posts a letter of credit. A letter of credit is a bank’s promise to pay Duke if the customer does not. A customer that ends its contract early owes set damages. Duke Energy Carolinas fact sheet

The order also requires Duke to file an estimate of each customer’s share of network upgrade costs for the commission to review and approve. Its newest term is a stranded generation charge. That charge covers the part of a new power plant left unpaid if a data center stops service before the plant wears out. The order estimates it from a model gas plant with a 35 year life, at $67,357 per megawatt each year. A stakeholder group will develop a permanent method for this charge, a standard service contract, and the method for assigning upgrade costs. North Carolina Utilities Commission order Duke told investors it is still assessing this part of the order. Duke Energy Form 8-K

TermOctober agreementCommission order
Who is coveredAny customer of 50 megawatts with steady use, or 150 megawattsData centers of at least 50 megawatts
Contract signing dateOnly contracts signed on or after June 1, 2026Signing date does not decide coverage
Shared grid upgradesBank guarantee, direct charge only after a future methodDuke files each customer’s estimated share for commission review
New power plantsNo separate chargeStranded generation charge of $67,357 per megawatt each year
Rate scheduleDuke’s existing schedule for large steady usersA new schedule only for data centers

A commissioner dissents in part over costs left to other customers

In the companion order for Duke Energy Progress, one commissioner dissented in part. He wrote that the plants are built to last about 35 years while the contracts run 15. He argued that even when a departing data center pays everything required, about half of the remaining plant cost can stay with other customers. Carolina Journal

He gave an example of a 500 megawatt data center that could require about $674 million of new equipment. If that customer left after 15 years, he wrote, it would pay about $338 million, and the other $335 million would fall on remaining customers. Environmental Defense Fund He would have required data centers to pay in advance for the generation and transmission their demand needs.

The Compute Law Briefs

Five minutes a day so you don’t miss the law behind the biggest infrastructure buildout.

A free email every weekday on AI data center law. New rules, project updates, and some other nerdy stuff that I come up with.

More on AI data center law

AI Data Center Incentives Map

Map

Free Guides and Daily Briefs on AI Infrastructure Law

Home

Power purchase agreements for AI data centers

Power

Florida utility connection and power contracts for AI data centers

Power

Large load grid connection and study agreements for AI data centers

Power