NYISO is the nonprofit that runs New York’s high voltage grid and its wholesale power markets. FERC is the federal agency that oversees regional grid operators. In June, it found that NYISO’s rules for connecting very large new power users, such as AI data centers, may be unfair because they lacked clear terms. FERC told NYISO to defend those rules or propose new ones. FERC order NYISO’s top committee of members has now approved new rules, after NYISO added a category it calls State Exempt Large Load. RTO Insider reports that the category is meant to account for rules New York has not yet issued. RTO Insider
Which loads count as large
Under NYISO’s September draft, a large load is a business or industrial site that can draw 50 megawatts or more from the state’s high voltage grid. A megawatt is one million watts. Sites within 2 miles and two grid connection points of each other, in the same region of the state, are counted together. A developer therefore cannot split one campus into small pieces to stay under the line. NYISO
The October draft excludes loads that cannot safely be switched off, such as hospitals, first responder facilities and public water facilities. Zero Emission Grid Today NYISO studies loads over 10 megawatts at 115 kilovolts or more, or 80 megawatts or more at lower voltage. The developer receives that study for information only, and it does not require anyone to do anything. NYISO
What a covered project would face
NYISO says a large load must not leave the state with fewer power plants than it needs. A project can meet that test by pairing with new supply, either on its own site or elsewhere in the same region. It can also accept non-firm service. Non-firm service means the grid cuts the site’s power first when supply runs short.
NYISO gives an illustrative example in its draft. A 100 megawatt load in Zone B with no new supply would receive 100 megawatts of non-firm service. NYISO
The October draft adds a deposit of $4,000 per megawatt to enter the final study. A project then has 14 calendar days to accept its share of upgrade costs or be withdrawn. Zero Emission Grid Projects already waiting are sorted into three groups. Nineteen projects totaling 3.7 gigawatts would finish their current studies. Twenty seven projects totaling 9.7 gigawatts would go through a transitional study, and two projects totaling 0.8 gigawatts would be withdrawn and could reapply.
| What changes | Today | Under the proposal |
|---|---|---|
| Size covered | Over 10 megawatts at high voltage | 50 megawatts or more, nearby sites added together |
| What the study does | Informs the developer only | Decides firm or non-firm service |
| New power supply | No requirement | Pair with new supply or accept cuts first |
| Hospitals and water plants | Same process as others | Left out of the definition |
| Final study deposit | $150,000 study deposit | $4,000 per megawatt |
The $150,000 figure is the current study deposit for a load study. Keentel Engineering
Where New York’s own review comes in
New York is writing its own rules at the same time. The Public Service Commission, the state body that sets utility rates, opened a case on February 12, 2026. The case asks how to define large loads, how to split grid upgrade costs, and whether data centers should bring their own supply or accept cuts. The commission’s staff must issue a white paper within one year, so by February 12, 2027. Public Service Commission
The governor’s July 14 executive order directed an environmental review of data centers. It also paused certain state environmental permits for facilities that can draw 50 megawatts or more. FingerLakes1 Public comments on the scope of that review closed on October 20. Public Service Commission
FERC’s own order says states keep control over retail power sales, over who may sell power to a large load, and over siting. FERC order Which projects fall into the State Exempt Large Load category, and what NYISO will still require of them, depends on state rules that do not exist yet.
Support inside NYISO was thin. RTO Insider reports that most members abstained in the earlier committee votes and that some state agencies opposed the framework. RTO Insider The state’s utilities are filing separately. They propose cost recovery agreements of 10 to 20 years and say those terms may change once the commission’s case ends. Zero Emission Grid
The timeline
NYISO told FERC it would file its proposal on November 16, 2026, once its members’ committee and its Board of Directors approved it. NYISO motion The members’ committee has approved it. The commission’s white paper is due by February 12, 2027.