The Oregon Public Utility Commission approved a new tariff on November 13, 2026 that makes new large data centers in Pacific Power’s Oregon service area pay the full cost of their electric service. A tariff is the published set of prices and terms a utility must offer a type of customer. The new Pacific Power tariff takes effect January 1, 2027. KTVZ
What the Oregon commission approved
The tariff came out of an agreement this fall between Pacific Power, the commission’s own staff, the Oregon Citizens’ Utility Board and the Green Energy Institute. KTVZ The tariff creates a new customer class for sites that use, or are able to use, 20 megawatts or more for computing, data processing or web hosting. A megawatt is a million watts. A site drawing 20 megawatts all day uses 480,000 kilowatt hours, the same unit a home electric bill counts. Grants Pass Tribune A Pacific Power senior vice president said the approach makes new large energy users cover their own costs while the state keeps attracting investment. KTVZ
What the POWER Act requires of tariffs and contracts for large computing sites
The POWER Act is House Bill 3546, a 2025 Oregon law that took effect June 16, 2025, the day it was signed. Policy tracker Before the law, large computing sites were billed in the same industrial class as other large customers. JPR The law now requires a separate class, with its own tariff, for any facility using or able to use 20 megawatts or more that mainly provides computing infrastructure, data processing or web hosting. The tariff must either charge that class its cost of service or assign each facility’s costs directly to it. The tariff must also lower the risk that other customers pay costs those facilities cause. HB 3546
Every contract with a covered facility must last at least 10 years and state the date, or estimated date, service will begin. The contract must require a minimum payment, set by the commission and based on projected use, even if the facility uses less power than planned. It may add a charge when a facility draws more than its contract allows. HB 3546
| What the law changed | Before the POWER Act | After the POWER Act |
|---|---|---|
| Customer class | Billed in the general industrial class | Separate class with its own tariff |
| Who carries the cost | No rule aimed at large computing sites | Charged to the class or assigned to each facility |
| Contract length | No minimum set by state law | At least 10 years |
| Minimum payment | No state requirement | Required, based on projected use, amount set by the commission |
| Start date | Not required in a contract | Contract states the date or estimated date service begins |
| Use above the contract | No state rule | Contract may add a separate charge |
What a new AI data center must pay and sign before service
The approved Pacific Power tariff requires contracts lasting between 10 and 30 years. Grants Pass Tribune A customer pays for the engineering studies on its project and a $25,000 application fee it does not get back. Each customer also has its own exit fee, an amount owed if it leaves before Pacific Power recovers what it spent to serve that site. Pacific Power checks each customer’s credit or requires collateral, which is money or a guarantee pledged up front in case the customer cannot pay.
Facilities over 100 megawatts pay an extra charge of 1 cent per kilowatt hour. That money pays for energy efficiency work, needed home repairs and small local power sources for low income Pacific Power customers in Oregon. The Data Center Coalition objected to parts of the agreement, including its costs and flexibility. The commission approved the settlement over those objections. Pacific Power’s revised tariff pages are due November 24. Grants Pass Tribune
Which existing sites the new rules reach
The law’s contract rules apply to a contract signed before June 16, 2025 in only one case. Serving that customer must require the utility to make significant investments or incur costs after that date that could raise costs or risks for other customers. HB 3546 Pacific Power said in its October 2025 filing that it planned to address existing covered facilities in its next general rate case. Pacific Power filing Amazon Data Services argued that Pacific Power’s first draft applied the law more broadly than the law allows. The company said the draft left out the condition about raising costs or risks for other customers. Amazon petition
Tomorrow’s topic
The ISO-NE large load proposal filed with FERC.
