Oregon regulators approve Pacific Power rules for large AI data center customers

The Oregon Public Utility Commission approved a new tariff on November 13, 2026 that makes new large data centers in Pacific Power’s Oregon service area pay the full cost of their electric service. A tariff is the published set of prices and terms a utility must offer a type of customer. The new Pacific Power tariff takes effect January 1, 2027. KTVZ

What the Oregon commission approved

The tariff came out of an agreement this fall between Pacific Power, the commission’s own staff, the Oregon Citizens’ Utility Board and the Green Energy Institute. KTVZ The tariff creates a new customer class for sites that use, or are able to use, 20 megawatts or more for computing, data processing or web hosting. A megawatt is a million watts. A site drawing 20 megawatts all day uses 480,000 kilowatt hours, the same unit a home electric bill counts. Grants Pass Tribune A Pacific Power senior vice president said the approach makes new large energy users cover their own costs while the state keeps attracting investment. KTVZ

What the POWER Act requires of tariffs and contracts for large computing sites

The POWER Act is House Bill 3546, a 2025 Oregon law that took effect June 16, 2025, the day it was signed. Policy tracker Before the law, large computing sites were billed in the same industrial class as other large customers. JPR The law now requires a separate class, with its own tariff, for any facility using or able to use 20 megawatts or more that mainly provides computing infrastructure, data processing or web hosting. The tariff must either charge that class its cost of service or assign each facility’s costs directly to it. The tariff must also lower the risk that other customers pay costs those facilities cause. HB 3546

Every contract with a covered facility must last at least 10 years and state the date, or estimated date, service will begin. The contract must require a minimum payment, set by the commission and based on projected use, even if the facility uses less power than planned. It may add a charge when a facility draws more than its contract allows. HB 3546

What the law changedBefore the POWER ActAfter the POWER Act
Customer classBilled in the general industrial classSeparate class with its own tariff
Who carries the costNo rule aimed at large computing sitesCharged to the class or assigned to each facility
Contract lengthNo minimum set by state lawAt least 10 years
Minimum paymentNo state requirementRequired, based on projected use, amount set by the commission
Start dateNot required in a contractContract states the date or estimated date service begins
Use above the contractNo state ruleContract may add a separate charge

What a new AI data center must pay and sign before service

The approved Pacific Power tariff requires contracts lasting between 10 and 30 years. Grants Pass Tribune A customer pays for the engineering studies on its project and a $25,000 application fee it does not get back. Each customer also has its own exit fee, an amount owed if it leaves before Pacific Power recovers what it spent to serve that site. Pacific Power checks each customer’s credit or requires collateral, which is money or a guarantee pledged up front in case the customer cannot pay.

Facilities over 100 megawatts pay an extra charge of 1 cent per kilowatt hour. That money pays for energy efficiency work, needed home repairs and small local power sources for low income Pacific Power customers in Oregon. The Data Center Coalition objected to parts of the agreement, including its costs and flexibility. The commission approved the settlement over those objections. Pacific Power’s revised tariff pages are due November 24. Grants Pass Tribune

Which existing sites the new rules reach

The law’s contract rules apply to a contract signed before June 16, 2025 in only one case. Serving that customer must require the utility to make significant investments or incur costs after that date that could raise costs or risks for other customers. HB 3546 Pacific Power said in its October 2025 filing that it planned to address existing covered facilities in its next general rate case. Pacific Power filing Amazon Data Services argued that Pacific Power’s first draft applied the law more broadly than the law allows. The company said the draft left out the condition about raising costs or risks for other customers. Amazon petition

Tomorrow’s topic

The ISO-NE large load proposal filed with FERC.

The Compute Law Briefs

Five minutes a day so you don’t miss the law behind the biggest infrastructure buildout.

A free email every weekday on AI data center law. New rules, project updates, and some other nerdy stuff that I come up with.

More on AI data center law

AI Data Center Incentives Map

Map

Free Guides and Daily Briefs on AI Infrastructure Law

Home

Power purchase agreements for AI data centers

Power

Capacity reservation and take-or-pay contracts for AI compute

Deals

Large load grid connection and study agreements for AI data centers

Power