PJM asks FERC for a 12 month grid study for AI data centers

What did PJM file?

PJM is the organization that runs the high voltage power grid across 13 states in the Mid Atlantic and Midwest. Reuters via NST On November 16, 2026, it asked the Federal Energy Regulatory Commission to approve a new study process it calls Fast Energization. The commission, called FERC, is the federal agency that approves the rules for the interstate grid. PJM says the change would cut the projected time to study a new power plant or a large power user, such as an AI data center, from two years to one. PJM Inside Lines

A study here is an engineering check of whether the grid can safely take a new connection, and what upgrades it needs first. Today PJM studies power plants and large users in separate processes. Under the plan, both would be studied together in one yearly cycle, and states and utilities would get clear insight into who pays for the upgrades. PJM Inside Lines

The plan applies to a Large Load. FERC accepted that definition on October 9. A Large Load is a customer site with a combined peak demand of 50 megawatts or more. Colocation Scout

What a developer must submit and prove in PJM’s yearly study cycle

PJM presented the design to its members in October. Each yearly cycle runs four months of screening, seven months of detailed study and one month to sign the final agreement. PJM presentation The screening gives a developer early results before most of its money is at risk.

A developer applies by naming its grid connection point and its megawatts. It also says whether the site will be paired with its own generation, picks a transmission service, and submits a site plan and a study deposit. A project is then dropped before the detailed study unless it meets several conditions. It must post a readiness deposit, which is money that shows the project is real. It must also prove it controls the site, list its permits and supply technical data. A Large Load must also show its transmission owner approved, including a signed cost agreement. PJM presentation

What changesBeforeAfter, if FERC approves
Study timeAbout two yearsAbout 12 months
Plants and large usersStudied in separate processesStudied together in one cycle
Proof a project is realRequired later in the processRequired before the detailed study
Service while upgrades are builtFull firm service onlyInterruptible service allowed in the meantime
Cost commitmentNegotiated case by caseA standard agreement with the transmission owner

The new service options include interruptible service while upgrades are built, and capped service on a firm or interruptible basis. American Public Power Association

Who signs the cost agreement and for how long

The transmission owners are the utilities that own the power lines. They hold the right to file cost and rate rules, and they filed their own proposed tariffs on November 16. Utility Dive via Yahoo

In an October notice, the owners described a cost recovery agreement. That is a contract that makes a large user pay for the grid upgrades built for it, even if the site never fills up. The owners were weighing a term of 10 to 20 years after service begins. The user would owe a minimum payment based on the megawatts it requested, plus a charge if it takes less. A letter of credit or similar security would back the payment. Transmission owners notice The owners also said they might let some existing private agreements with large users stay in place. Transmission owners notice

When the new rules would apply

PJM told its members the new study process would apply to requests submitted after an effective date it sets. PJM response matrix A large user already on the grid is treated differently. Its current service goes on a registry as a baseline, and only a new request or an increase above that baseline must apply and be studied. American Public Power Association

PJM asked FERC to set a 60 day comment period and to rule within 120 days. PJM Inside Lines Counted from November 16, a ruling on that schedule would come by March 16, 2027. Answers in the related FERC proceeding on large loads are due December 16, 2026. Tom Killi

Not every user supports the plan. The Data Center Coalition, a trade group, told PJM’s board in October that combining the studies could make the process harder and cause longer delays. Reuters via NST

A separate PJM filing sets a different date. It would require large computing sites of 50 megawatts or more to stay connected through brief grid disturbances, starting January 16, 2027. Existing sites would get one year to comply. PJM Inside Lines

Tomorrow’s topic

The Senate permitting bill’s data center provisions.

The Compute Law Briefs

Five minutes a day so you don’t miss the law behind the biggest infrastructure buildout.

A free email every weekday on AI data center law. New rules, project updates, and some other nerdy stuff that I come up with.

More on AI data center law

AI Data Center Incentives Map

Map

Free Guides and Daily Briefs on AI Infrastructure Law

Home

Large load grid connection and study agreements for AI data centers

Power

How AI data centers connect to the grid (FERC and the power queue)

Power

Demand response and curtailment for large AI data centers

Power