PJM begins deciding which AI data centers count in its 2027 forecast

PJM is the organization that runs the electric grid and the wholesale power market across 13 Mid-Atlantic and Midwest states and the District of Columbia. Utility Dive On September 29, 2026, twelve utilities presented requests asking PJM to add new demand, mostly from AI data centers, to its load forecast. A load forecast is PJM’s estimate of how much power customers will use in future years. PJM buys power plant capacity and plans new transmission lines against that estimate, so a project left out of it is a project nobody is building the grid to serve. PJM Inside Lines

What PJM is reviewing this fall

The rules for this review sit in Attachment B of PJM’s Manual 19, in the version that took effect on June 30, 2026. A utility can ask for an adjustment when it expects a load shift of 50 megawatts or more. A megawatt measures how much power a site draws at one moment. Utilities were asked to tell PJM by August 1 that they planned to file, and the full requests went in during September. PJM Manual 19

The stakes show in last year’s numbers. For 2030, utilities asked PJM to add roughly 60 gigawatts of demand across its whole region. PJM accepted 34 gigawatts. Modo Energy

What makes a project count as firm?

Only firm demand can count toward the years covered by a capacity auction. A capacity auction is how PJM pays power plants years ahead to be available when needed. The manual calls a project firm when it has two things. The first is a binding promise from the customer to take and pay for the power, or a utility commitment to build the lines with the customer paying toward them. A long term supply deal also counts. The second is real money behind it, such as collateral or an investment in the needed infrastructure.

Everything else is non firm. PJM may still count non firm demand, but only for later years that no auction has covered yet. PJM can also lower even firm numbers if supply chains or industry trends would slow the build. A signed letter with no money behind it will not move a near term forecast.

What a utility has to hand over

The manual asks for detail on each project. That means the owner, the location, the status of site control and permits, and the kind of data center. It also covers when the load starts, how fast it grows, whether it sits next to a power plant, and the customer’s financial terms. Customer secrecy agreements must allow the utility to share all of it with PJM. Missing data makes the request incomplete, and PJM may reject it or cut it down.

Utilities must also ask each customer whether the same project has asked to connect somewhere else, inside or outside PJM. A customer that does not answer is treated as a duplicate. If a utility flags a duplicate but cannot give the number of sites and megawatts, PJM removes that request from consideration. PJM Manual 19

The 2021 version of the same attachment asked for far less. PJM Manual 19, 2021

Issue2021 manualManual in force since June 30, 2026
State utility regulatorNo role in the reviewMust get a chance to review before September filing
Loads counted for auction yearsNo firm testOnly loads with binding contracts and money behind them
Duplicate requestsNot asked aboutUnanswered questions count as duplicates
Customer secrecy agreementsNot addressedMust allow sharing all relevant data with PJM
Outside reviewAny available independent analysisOutside forecast can pull the final number toward its baseline

Who else checks the numbers

Before filing, each utility must give its state utility regulator a chance to review the request and comment. A regulator that stays silent is treated as waiving that chance. PJM will say publicly whether a review happened but will not reveal what the regulator said. PJM Manual 19

PJM has also hired Charles River Associates to study AI data center demand trends on its own. That firm presents its findings in October. PJM then compares the utilities’ firm and non firm totals with that outside forecast and its range of uncertainty. Where the utility total falls outside that range, the final figure becomes an average of the outside baseline and the regulator’s view. If the final figure lands above what a utility asked for, the utility may keep its own lower number.

PJM plans to show how it combined all of this in November. The 2027 long term load forecast is due in January. PJM Inside Lines

Tomorrow’s topic

The Michigan PSC approval of the DTE power contract for Google.

The Compute Law Briefs

Five minutes a day so you don’t miss the law behind the biggest infrastructure buildout.

A free email every weekday on AI data center law. New rules, project updates, and some other nerdy stuff that I come up with.

Related guides

Large load grid connection and study agreements for AI data centers

Power

How AI data centers connect to the grid (FERC and the power queue)

Power

Demand response and curtailment for large AI data centers

Power

Power purchase agreements for AI data centers

Power

Virginia PJM market and Dominion power service for AI data centers

Power
More from Compute Law Blog

AI Data Center Incentives Map

Map

Free Guides and Daily Briefs on AI Infrastructure Law

Home