The Senate is working through a permitting bill that would make AI data centers pay the whole cost of the power lines that serve them. Its sponsors filed the current version as a full substitute for the text of an unrelated House bill, H.R. 2347. THE LAW
Senate votes so far and steps left before the bill becomes law
The Senate voted 73 to 25 on November 9 to take up the bill. The bill now goes through amendments before a final Senate vote. EPW Committee On November 18 the Senate agreed to another motion on the bill by 70 to 26, on a vote that needed three fifths of senators. Senate roll call The bill still needs a final Senate vote, House passage and a signature. None of what follows is law yet.
What the bill says AI data centers must pay
Section 2107 opens with findings Congress would adopt as national policy. Owners and operators of these sites would pay the full cost of the electric service they need and of any equipment built to serve them. They would owe that cost even if they never take the power they asked for. THE LAW Under that policy, a site that requests service and then never uses it would still carry the cost of lines built for it.
The findings focus on transmission. Transmission means the high voltage lines that carry power long distances before local utilities deliver it. A utility rate would fail the federal legal test for utility rates if it charged a covered site less than two amounts. The first is the embedded cost, a term the bill uses but does not define. The second is the incremental cost, meaning the new lines and upgrades needed because the site connected.
Those costs would be assigned in full to the site. The stated goal is to keep them off other customers, including households.
Which sites the bill covers
The bill covers a computational load site. That is one or more buildings at a single location that mainly hold computer equipment for software, AI training, cryptocurrency mining or similar work, and that connect to the main power grid. A factory whose computers only support its own production is excluded. The bill leaves the exact list of covered customers to FERC, the federal agency that regulates interstate power lines, to set by rule or order. THE LAW A law firm analysis reports that separate state protections in the bill reach data centers and high density computing loads of at least 20 megawatts. Law firm analysis
| Item | Before | Under the bill |
|---|---|---|
| How AI data centers pay for lines | Voluntary arrangements | Full cost assigned to the site |
| Paying for unused service | No statutory policy | Site pays even if unused |
| Lowest lawful rate | No statutory floor | Embedded plus incremental cost |
| Which sites are covered | No federal definition | FERC decides by rule or order |
| Deadline to revise pricing guidance | 270 days in the September version | 90 days after enactment |
What FERC would have to do, and how fast
FERC would have 90 days after the bill becomes law to rewrite its 1994 guidance on how utilities price transmission. The new guidance would require utilities to charge covered sites the embedded cost plus a reasonable share of the incremental cost, with FERC setting that share. THE LAW The September version of the bill gave FERC 270 days instead. Committee section-by-section
The committee summary of that September version describes more steps. A site choosing service that can be cut off when the grid is stressed would pay a lower rate. FERC would then propose a rule requiring utilities to set rates for these customers and to study which upgrades each site needs. States could set their own separate rates for data centers, including charging both embedded and incremental costs. A state could also run a competitive process and use any extra money to lower other customers’ rates. The summary says the section neither expands nor shrinks federal or state power over rates.
What the money and the support would look like
The Senate energy committee’s ranking member cites a Grid Strategies estimate that AI data centers would pay about $55 billion in transmission costs over the next decade under the bill. That is about $35 billion more than under current policy. Senate Energy Committee
The substitute also adds a Department of Energy program, in section 2117, to help state, local and Tribal governments review proposed AI data centers. The help covers what a project would mean for power supply, costs, water, infrastructure and the local economy before a community grants a permit. Senate Energy Committee
