What California's new data center laws make developers disclose and pay

California’s governor signed seven bills on September 21, 2026 that set new rules for data centers on electricity, water and land use. Governor’s office The laws take effect January 1, 2027. Law firm analysis Each duty lands at a different point in a project’s life, and a different body enforces it.

What a developer tells the city or county first

A city or county may not approve a permit to build a data center until the developer hands over a water supply assessment. That is a study, done under the state Water Code, of whether local supplies can meet the project’s needs. AB 2469 Until now that study was required only for projects above certain size or water use thresholds. UC Berkeley report The same rule covers an expansion that raises peak water use. The developer must also give projected water use, water saving measures, and an estimate of its workforce, including wages and how many workers live locally.

A second law adds an energy and noise estimate. With a discretionary permit application, the developer gives the local agency its expected yearly electricity use and expected onsite generation, backup generators included. AB 1577 It must also estimate average and maximum noise at the loudest point on the property line.

Before applying for a first business license, the operator sends its water supplier a good faith estimate of water use. The estimate names the water source and the expected volume on the peak day, the peak month and an average year. AB 2619 The operator signs it under penalty of perjury, meaning a knowingly false figure is a crime.

What goes to the state once the power is on

The California Energy Commission, the state’s energy planning agency, collects ongoing figures from any facility with at least 10 megawatts of electrical capacity. A megawatt measures how much power a site can draw at once. When first switched on, the owner files basic facts such as floor area and expected peak demand. After that it reports at least yearly, broken out by month, covering electricity use, backup fuel burned and cooling refrigerants. AB 1577 The law gives the commission no deadline to set up this filing process.

At each business license renewal, the operator also reports last year’s actual water use and its cooling system type. AB 2619

Who pays for new pipes and power lines

The developer pays the full cost of new water pipes, treatment or storage needed to serve the site, in the amount the water supplier sets. AB 2469 Electricity costs run through the California Public Utilities Commission, which must adopt new tariffs for data centers by January 1, 2028. SB 886 A tariff is the official price list and rulebook a utility files for a class of customers.

For a data center taking power from high voltage lines, the tariff assigns it the cost of every transmission upgrade. Refunds of its upfront payment are capped at 75 percent of the yearly transmission revenue it brings the utility. A site that leaves within 10 years, or never reaches its projected load, owes an early termination fee. That fee cannot be less than the revenue the utility expected to lose.

A companion law covers the power supply itself. Each utility’s generation tariff must make a data center pay, for at least 10 years, for new supply its load requires. AB 2383 It requires upfront collateral or prepayment, and a minimum payment based on projected load. The commission cannot set the size threshold above 25 megawatts.

What changedBefore the lawsAfter the laws
Water study before a local permitOnly projects above set size or water thresholdsEvery data center permit, with no size threshold
Water estimate to the supplierNot required, after a 2025 vetoRequired before a first business license, under penalty of perjury
Energy report to the stateNo data center specific reportYearly filing for sites of 10 megawatts or more
Transmission upgrade costsSettled in one off utility filingsAssigned to the data center by tariff
Water infrastructure costsLeft to the water supplier and developerPaid in full by the developer

When each duty starts

The permit, license and reporting duties start January 1, 2027, except the water scarcity plan. That plan becomes a permit condition on January 1, 2028. It must set out staged cuts in water use for each level of drought, from abnormally dry to exceptional. AB 2469

The transmission tariff reaches only a data center that signs a new high voltage connection agreement on or after January 1, 2027. A project needing service before the commission finishes may get a one off contract approved, if it follows the same rules. SB 886 Community energy providers that buy power for local customers face a January 1, 2028 deadline for their own data center generation tariffs. AB 2383

Tomorrow’s topic

New Jersey’s $1.1 million fine over an AI data center’s unpermitted generators.

The Compute Law Briefs

Five minutes a day so you don’t miss the law behind the biggest infrastructure buildout.

A free email every weekday on AI data center law. New rules, project updates, and some other nerdy stuff that I come up with.

Related guides

Easements and eminent domain for AI data center power lines

Real Estate

Energy and water use reporting for AI data centers

Real Estate

Power purchase agreements for AI data centers

Power

Large load grid connection and study agreements for AI data centers

Power

Air permits for AI data center backup generators

Real Estate
More from Compute Law Blog

AI Data Center Incentives Map

Map

Free Guides and Daily Briefs on AI Infrastructure Law

Home