Vol. I · No. 001Updated every weekdayAlways free

Virginia fiber rights-of-way and pole attachments for AI data centers

In short

Virginia law divides pole attachment oversight between the Federal Communications Commission and the Virginia State Corporation Commission. Investor owned electric utility poles, like those of Dominion Energy and Appalachian Power, fall under FCC rules. Electric cooperative poles are regulated by the SCC through a statute amended in 2024. Va. Code § 56-466.1 The 2024 amendments set mandatory timelines for application review, make ready work, and cost estimates, and they give the SCC authority to resolve disputes in 90 or 120 days. Fiber providers can also use limited access highway rights of way under long-term shared resource agreements with the Virginia Department of Transportation, and existing utility easements generally allow broadband use without additional landowner approval, though a communications provider must enter into an agreement with the incumbent utility. 24 VAC 30-151-30, Va. Code § 55.1-306.1 Recent federal and state decisions have limited what pole owners can charge new attachers for pole replacements, reducing cost uncertainty for AI data center fiber builds.

Why fiber access matters for AI data centers in Virginia

Northern Virginia is the largest market for AI data centers in the world. The region hosts dozens of hyperscale AI data centers that rely on fiber optic cables to move enormous amounts of data. A 680 mile dark fiber network connects the AI data centers in Loudoun County (Data Center Alley) to the Virginia Beach cable landing station that receive two major subsea cables, MAREA at 200 terabits per second and BRUSA at 138 terabits per second. News alert, VEDP analysis, News report Building new fiber routes requires the right to attach cables to utility poles and the right to occupy public rights of way. Virginia law governs both, but the rules differ depending on who owns the pole and where the road runs. Developers and fiber providers must understand the split jurisdiction to control costs and timelines.

The three layers of pole attachment regulation in Virginia

Virginia does not have a single set of pole attachment rules. The law creates three separate paths based on the type of utility that owns the pole. The most important divide is between investor owned utilities (regulated by the FCC) and electric cooperatives (regulated by the State Corporation Commission under a 2024 law). A third, smaller category covers telephone cooperatives and small telephone companies.

Utility typeRegulatorKey statuteNotable feature
Investor owned electric utilities (Dominion Energy, Appalachian Power)FCC47 U.S.C. § 224Virginia has not reverse preempted the FCC. The FCC sets rates and resolves disputes.
Electric cooperatives (for example, NOVEC)SCCVa. Code § 56-466.1 (2024)New statutory deadlines, SCC dispute resolution, and a red tagged pole rule apply.
Telephone cooperatives, mutuals, and small investor owned telephone utilitiesSCCVa. Code § 56-41.1A public interest declaration exists. The SCC sets rates if no agreement is reached.

Investor owned utility poles stay under FCC control

The federal Pole Attachment Act, 47 U.S.C. § 224, gives the FCC authority over pole attachments by telecommunications and cable providers to investor owned utility poles. 47 U.S.C. § 224 States can reverse preempt the FCC and regulate all pole attachments themselves, but Virginia has chosen not to do that. FCC public notice As a result, the two largest investor owned electric utilities in Virginia, Dominion Energy and Appalachian Power, handle pole attachments under FCC rules and their own published policies. Dominion Energy Pole Attachments page, APCO Pole Attachment Policy

FCC rules set a standard formula for pole attachment rates, but disputes about cost allocation and access still arise. In February 2026, the FCC ruled in a case involving Appalachian Power that a utility may not charge a new attacher the full cost of replacing a pole that already fails to meet safety or engineering standards. The attacher pays only the incremental cost of a stronger or taller pole needed for the new attachment. FCC 26-6 This ruling applies to Appalachian Power poles in Virginia and significantly limits the cost exposure for fiber providers.

Electric cooperative poles are now regulated by the SCC under a detailed timetable

Electric cooperatives are member owned utilities. They are not subject to FCC pole attachment regulation because 47 U.S.C. § 224(a)(1) expressly excludes any person who is cooperatively organized. 47 U.S.C. § 224(a)(1) For decades, Virginia cooperative pole attachments were governed by contract and by a general statute, Va. Code § 56-466.1, that offered little enforcement machinery. In 2024, the General Assembly passed HB 800 and SB 713, which rewrote the statute and gave the SCC a active enforcement role. The amendments took effect July 1, 2024. Va. LIS HB 800, Va. LIS SB 713

The amended statute defines the key terms. A pole attachment is any attachment by a cable television system or provider of telecommunications service to a pole, duct, conduit, right-of-way, or similar facility owned or controlled by a public utility. Va. Code § 56-466.1(A) A public utility here has the same meaning as in Va. Code § 56-232 but excludes any utility regulated under 47 U.S.C. § 224. Va. Code § 56-466.1(A) A new attacher means a cable television system or telecommunications service provider requesting a new pole attachment. Rearrangement means work necessitated solely by and at the request of a telecommunications service provider or cable television system to make an existing pole, duct, conduit, right-of-way, or similar facility usable for a pole attachment, including replacement if the existing facility does not contain adequate surplus space or excess capacity and cannot be rearranged to create it. A red tagged pole means a pole owned or controlled by a public utility that is designated for replacement for any reason unrelated to a lack of capacity to accommodate a new attacher’s request for attachment, or one that would have needed to be replaced at the time of replacement even if the new attachment was not made. Va. Code § 56-466.1(A)

The SCC’s new role is to enforce the statute and to decide disputes when good faith negotiations between a cooperative and a would be attacher fail. The SCC must resolve disputes about pole access, including rearrangement cost allocation, within 90 days, and all other disputes within 120 days. Either deadline can be extended by up to 60 days by order of the Commission. Va. Code § 56-466.1(H) The SCC also has authority to set just and reasonable rates, and terms and conditions of service, excluding safety and debt collection for attachments to electric cooperative poles if the parties cannot agree. In doing so, it must consider the effect on broadband deployment, the interests of cooperative members, and the overall public interest. Va. Code § 56-466.1(H)

Telephone cooperatives and small telephone companies have their own path

A separate statute, Va. Code § 56-41.1, declares that joint use of poles by electric companies and telephone cooperatives, mutual telephone associations, and small investor owned telephone utilities is in the public interest. Va. Code § 56-41.1 Rates and terms are set by agreement, but if the parties cannot agree, the SCC steps in to determine them. This statute is less detailed than § 56-466.1 and has been used less often for large AI data center fiber builds, but it still applies where telephone cooperatives own the poles.

What the 2024 amendments changed for cooperative pole attachments

The 2024 rewrite of § 56-466.1 added a step by step process with specific deadlines that both the cooperative and the new attacher must follow. The main thrust is to speed up the attachment process and reduce uncertainty.

The statutory deadlines that now apply are summarized below.

What must happenDeadline
Cooperative determines if application is complete15 business days (application deemed complete if no response)
Cooperative reviews a resubmitted application7 business days to respond (deemed complete if silent)
Cooperative grants or denies the application75 days (runs concurrently with completeness review)
Cooperative completes a field survey of the poles75 days
Advance notice of any field inspection5 business days
Cooperative provides a make ready cost estimate20 days after granting access
The estimate remains open for acceptance30 days
Cooperative notifies existing attachers after paymentImmediately
Cooperative completes the make ready work95 days after the notice
Third party contractor must perform make readyIf the request pushes aggregate past the lesser of 300 poles or 0.5% of total poles in a month
SCC resolves a pole access dispute90 days (extendable by 60)
SCC resolves any other dispute120 days (extendable by 60)

Application review and survey

A new attacher submits a request. The cooperative must determine whether the application is complete within 15 business days and tell the attacher. If the cooperative stays silent, the application is automatically deemed complete after those 15 days. Va. Code § 56-466.1(G)(1)(a)(1) If the application is incomplete and the attacher resubmits, the clock resets to 7 business days for the cooperative to respond again. There is no limit on the number of resubmissions, as long as the attacher makes a bona fide attempt each time. Va. Code § 56-466.1(G)(1)(a)(2)

Once a complete application is on file, the cooperative must grant or deny the request within 75 days. This 75 day clock runs at the same time as the 75 day survey requirement in subdivision (G)(1)(c). If the cooperative does nothing, the application is not deemed granted. The statute does not provide a deemed grant remedy. Va. Code § 56-466.1(G)(1)(b) The cooperative must also complete a survey of the affected poles within 75 days and use commercially reasonable efforts to provide at least five business days’ advance notice of any field inspection to the new attacher and any existing attachers on those poles. Va. Code § 56-466.1(G)(1)(c)(1) and (G)(1)(c)(2)

Cost estimate and payment

Within 20 days after granting access, the cooperative must provide a detailed, itemized estimate of all rearrangement charges. The estimate must be pole by pole if requested and supported by documentation. Va. Code § 56-466.1(G)(2) The estimate stays open for 30 days. If the attacher does not accept it within that window, the cooperative may withdraw it. After the work is done, if the actual costs differ, the cooperative must give a final detailed invoice, again with pole by pole documentation if requested. Va. Code § 56-466.1(G)(2)(b)

Make ready work and completion

When the attacher pays, the public utility must immediately notify all known existing attachers that may be affected in writing. The notice sets a completion date no later than 95 days after the notice. The public utility must finish the rearrangement by that date. The new attacher is responsible for coordinating with existing attachers to encourage the completion of rearrangement by the completion date. Va. Code § 56-466.1(G)(3) and (G)(4)

The cooperative may extend the make ready deadline for good and sufficient cause as defined by the SCC. The SCC has not yet issued a rule or order defining that term, so this remains an open question. If the cooperative extends the deadline, it must give immediate written notice and a new completion date. Va. Code § 56-466.1(G)(5)

Large batch requests trigger a third party contractor

A request that pushes the cooperative’s total attachments or pending requests past the lesser of 300 poles or 0.5% of its total poles in a single month triggers a mandatory third party contractor rule. In that case, the cooperative shall negotiate in good faith to contract with a mutually agreed upon third party entity to perform the work. The cooperative keeps oversight and may assess the new attacher only for the actual reasonable costs of its oversight. Va. Code § 56-466.1(G)(6) This provision is designed to prevent a cooperative from using its own workforce as a bottleneck when a fiber provider needs to attach to a large number of poles quickly.

Red tagged pole cost protection

If a pole is a red tagged pole, already designated for replacement for unrelated reasons, the cooperative cannot recover the cost of replacing that pole from the new attacher. For a red-tagged pole, the attacher pays only the incremental cost of any stronger or taller replacement pole that is needed solely because of the new attachment. Va. Code § 56-466.1(G)(7) This rule mirrors the principle the FCC applied to investor owned utility poles in the 2026 Comcast v. APCO decision.

How cooperative pole attachment rates are set

Virginia law does not prescribe a fixed rate formula for cooperative pole attachments. The statute requires cooperatives and attachers to negotiate in good faith to reach a mutually agreeable contract. If they cannot agree following good faith negotiations, the SCC may determine just and reasonable rates, and terms and conditions of service, excluding safety and debt collection, for attachments to electric cooperative poles. Va. Code § 56-466.1(B) and (H)

The SCC has never adopted a uniform rate methodology for cooperatives. In a 2013 proceeding involving Northern Virginia Electric Cooperative (NOVEC) and Comcast, NOVEC initially asked for an annual rate of $30.92 per attachment. Comcast proposed $6.35. The SCC found that NOVEC had met its burden of proving its costs and ordered the parties back to negotiation. The Virginia SCC ultimately determined a rate of $20.60 per attachment per year. NRECA case study

The 2011 SCC report noted that annual pole attachment rates among Virginia cooperatives ranged from $3.38 to $65.41 at that time. 2011 SCC Report (at p. 22) No comprehensive public update of current rates was available, so a provider should expect to negotiate and, if needed, petition the SCC.

VDOT rights of way and fiber resource sharing

The Virginia Department of Transportation (VDOT) operates a fiber optic resource sharing program It allows private companies to install fiber optic conduit and cable in limited access highway right of way, such as interstates, in exchange for providing VDOT with fiber strands, conduit, or services for its own intelligent transportation system network. VDOT IIM-LU-303

A resource sharing agreement, or RSA, is the contract that governs the arrangement. The typical RSA term is 25 years, with an option to extend for another 25 years. If the fiber owner must relocate its facilities because of a VDOT road project, the fiber owner bears the relocation cost. An RSA does not replace a land use permit. The fiber provider must also obtain the necessary land use permits for construction. VDOT IIM-LU-303 VDOT may also seek monetary compensation for the use of the limited access right of way. 24 VAC 30-151-740

An RSA example is the 2020 agreement between VDOT and Osprey Communications for a multi conduit fiber system along the I-81 and I-66 corridors from Haymarket, Virginia to Nashville. The project includes six to seven conduits, each designed to carry 288 standard size fibers and 432 nonstandard fibers. Route Fifty That corridor runs near major AI data center hubs and shows the scale achievable under the RSA structure.

Using existing easements for broadband fiber

Virginia law encourages broadband deployment by treating existing utility easements as automatically available for broadband use. Under Va. Code § 55.1-306.1, absent any express prohibition on the installation and operation of broadband or other communications services in an easement that is contained in a deed or other instrument by which the easement was granted, the installation and operation of broadband or other communications services within any easement shall be deemed, as a matter of law, to be a permitted use within the scope of every easement for the location and use of electric and communications facilities. Va. Code § 55.1-306.1(D) This means a fiber provider can often string fiber along an existing utility easement without needing a new easement from the landowner, as long as the underlying easement does not say no broadband.

The statute also makes clear that using an easement for broadband is not considered a public use for purposes of eminent domain. Va. Code § 55.1-306.1(B)(6) This disclaimer was cited by the Virginia Supreme Court in 2025 when it struck down a different statute that attempted to take private property for railroad crossings for broadband purposes. The court held that the taking was for a private use, which violates the Virginia Constitution. Norfolk Southern Railway Co. v. SCC While the court did not rule on § 55.1-306.1 itself, the reasoning could invite a future challenge if a landowner argues that the automatic easement expansion is an unconstitutional taking. For now the statute remains in force and supports fiber builds.

Finally, the statute subjects any attachment to utility poles within the easement to the applicable rules. FCC rules govern investor owned utility pole attachments, and § 56-466.1 governs electric cooperative pole attachments. Va. Code § 55.1-306.1(O) So even if you have an easement, you must still follow the pole attachment process described above.

Recent disputes and what they mean for new fiber builds

Several recent cases illustrate how the rules are applied and where the friction points lie.

Comcast v. Appalachian Power (FCC 2026). Comcast is building broadband in Virginia under a $126 million federal BEAD grant and needed access to thousands of APCO poles. APCO’s policy charged new attachers the full cost of replacing poles with preexisting safety or engineering violations. The FCC ruled that this policy violated federal law. The attacher must pay only the incremental cost increase for a stronger or taller pole, not the full replacement cost. FCC 26-6 This decision directly limits what Appalachian Power can charge for pole replacements in Virginia, and it aligns with the red tagged pole rule that the 2024 Virginia statute imposed on cooperatives.

Dominion Energy v. Comcast (E.D. Va. 2010). Dominion sued Comcast for using over 192,000 attachments to provide telecommunications services while paying only the lower cable service rate. The federal court dismissed the claim under the Pole Attachment Act because there is no private right of action, sending the dispute to state law. Dominion v. Comcast, E.D. Va. 2010 The case shows the contractual nature and why a clear pole attachment agreement defining rates for each service matters.

NOVEC v. Comcast rate setting. The SCC proceeding that set a $20.60 rate for NOVEC’s poles showed that the SCC will step in when negotiations falter, but the process takes time and the outcome is fact specific. NRECA case study

Practical considerations for AI data center developers and fiber providers

Building fiber to an AI data center in Virginia means navigating a split regulatory system. Here are some practical points.

  1. Identify the pole owners early. In Northern Virginia, you may encounter a mix of Dominion Energy (IOU), NOVEC (cooperative), and possibly telephone cooperatives. Each follows a different set of rules.
  2. If you are attaching to cooperative poles, use the 2024 statutory process. Mark the deadlines. The 15 day completeness clock and the 75 day decision clock provide leverage.
  3. For large batches of cooperative pole attachments, monitor the 300 pole or 0.5% threshold. Crossing it will force the cooperative to accept a third party contractor, which can speed the work but adds a negotiation step to pick the contractor.
  4. On investor owned poles, the FCC ruling in Comcast v. APCO reduces your exposure to full pole replacement costs. Make sure the pole owner is not charging you for preexisting deficiencies.
  5. For highway right of way, consider an RSA with VDOT if your route follows interstates. The 25 year term and the ability to install multiple conduits can future proof the investment, but remember that relocation costs fall on you.
  6. Evaluate existing easements under § 55.1-306.1. Many rural and suburban fiber routes can be built along existing utility easements without needing new landowner consent, as long as the easement does not explicitly bar broadband. Check the deed language.
  7. Be aware of the constitutional uncertainty surrounding the easement statute after the Norfolk Southern case. A legal challenge is possible, but for now the statute provides a solid basis.
  8. If negotiations with a cooperative stall, petition the SCC. The 90 day (pole access) or 120 day (other) clock is relatively fast for a regulatory proceeding. The SCC guidelines require a detailed petition, but the process keeps things moving.

Key takeaways

  • Virginia pole attachment law is not one size fits all. The regulator depends on who owns the pole.
  • Investor owned utilities (Dominion Energy, Appalachian Power) remain under FCC jurisdiction. The 2026 FCC ruling prohibits charging a new attacher the full cost of replacing a pole with preexisting problems.
  • Electric cooperative poles are now regulated by the SCC under a 2024 statute with hard deadlines and new enforcement power. The SCC must resolve pole access disputes in 90 days.
  • The 2024 law sets a 75 day window for cooperatives to grant or deny a complete application, requires a survey in the same period, and mandates make ready completion within 95 days of notice.
  • A red tagged pole rule prevents cooperatives from shifting the cost of replacing an already failing pole onto the new attacher.
  • For large projects, the 300 pole or 0.5% trigger forces the cooperative to use a third party contractor for make ready work.
  • Pole attachment rates for cooperatives are negotiated, but the SCC can set just and reasonable rates. The NOVEC Comcast outcome ($20.60 per attachment) provides a benchmark.
  • VDOT offers 25 year resource sharing agreements for fiber along interstate right of way in exchange for fiber or services. The provider bears relocation costs.
  • Existing utility easements generally permit broadband fiber without new consent, but the constitutionality of that rule may be tested after a recent Virginia Supreme Court decision.

Frequently asked questions

Q:Who regulates pole attachments on Dominion Energy poles in Virginia?

A:The Federal Communications Commission regulates pole attachments on Dominion Energy poles under the federal Pole Attachment Act. Virginia has not chosen to regulate these poles itself.

Q:What changed in Virginia pole attachment law in 2024?

A:The General Assembly amended Va. Code § 56-466.1 to give the State Corporation Commission authority to enforce timelines and resolve disputes for attachments to electric cooperative poles. The law now sets specific deadlines for application review, surveys, cost estimates, and make ready completion.

Q:How long does a cooperative have to approve or deny a pole attachment application?

A:75 days after a complete application is filed. The completeness determination must happen in 15 business days, and the 75 day clock runs concurrently.

Q:What is a red tagged pole and who pays for its replacement?

A:A red tagged pole is one already scheduled for replacement for reasons unrelated to a new attachment. The new attacher does not pay for the full replacement, only the incremental cost if the replacement must be stronger or taller to accommodate the new attachment.

Q:Can I attach fiber to a pole without a contract?

A:No. Both the cooperative and the attacher must negotiate in good faith to reach a mutually agreeable contract. If they cannot agree, the SCC can step in.

Q:Does Virginia have a dig once policy for fiber along highways?

A:Virginia does not have a formal statewide dig once law, but VDOT has a long standing fiber resource sharing program that allows private fiber installation in interstate right of way under a resource sharing agreement.

Q:Do I need a new easement to string fiber on an existing utility easement?

A:Usually no. Virginia law treats the installation of broadband in an existing electric and communications easement as a permitted use, unless the easement document expressly prohibits it.

Q:What happens if a VDOT road project forces me to move my fiber?

A:Under a typical VDOT resource sharing agreement, the fiber owner must relocate its facilities at its own cost.

Q:Is the SCC fast track dispute process binding?

A:Yes. The SCC has authority to resolve disputes and its decision is binding unless appealed to the Virginia Supreme Court. The statute requires the SCC to act within 90 days for pole access disputes and 120 days for other matters.

Q:Can AI data center operators get a pole attachment agreement directly from a cooperative?

A:AI data center operators typically lease fiber from telecommunications providers that hold the agreements, but nothing in the statute prohibits an AI data center operator from seeking an agreement if it meets the definition of a cable system or telecommunications provider. Whether this has happened is not confirmed in public records.

Subscribe to The Compute Law Brief

The Compute Law Brief is a free weekday newsletter on the law of AI infrastructure across tax, real estate, construction, power, and deals. The big US build markets and federal law. Three minutes a morning. No paywall, and no email gate to read the blog. Subscribe if you want it in your inbox.

Junde Liu, JD, LL.M. (Taxation) candidate at UF Law. Originally published on Compute Law Blog. This article is general information and does not constitute legal advice. Reading it does not create an attorney client relationship. The reader should not act on the basis of any content here without first consulting a licensed attorney in the relevant state. Last reviewed for accuracy May 23, 2026.

The Compute Law Brief

One interesting idea worth knowing, every weekday

A free email every weekday on the law of building AI infrastructure, before you grab coffee.

This topic in other states

Florida fiber rights-of-way and pole attachments for AI data centers

Florida

Arizona fiber rights of way and pole attachments for AI data centers

Arizona

Texas fiber rights of way and pole attachments for AI data centers

Texas

Georgia fiber rights-of-way and pole attachments for AI data centers

Georgia
Related guides

Fiber and network connection agreements for AI data centers

Power

Dark fiber and long-term fiber agreements for AI data centers

Power

Long haul and middle mile fiber for AI data centers

Power

Carrier neutral connections and cross connects for AI data centers

Power

How submarine cable landings and access work for AI data centers

Power